Questions tagged [ms-project-2016]
61 questions
1
vote
0 answers
Ms project - removal of base calendar nonworking time not feeding through to resource calendars
I created recurring nonworking time on a base calendar. It correctly worked through onto the relevent resource calendars.
I added some nonworking time to individual resource calendars and all is still as expected.
However, when I go back to base…
IanElrick
- 11
- 1
1
vote
0 answers
Resource Assignments
I have 4 Work resources entered into the Resource sheet and each has standard rates. I assign the work resources to tasks, but one of the tasks continues to display $0.00. Then when I double-click the task that has the 4 Work resources assigned,…
Edward
- 11
- 1
1
vote
0 answers
How to update some Key information from another Project
I have created a Project in MS Project 2016. Of this data there are probably about 50 tasks which are of high importance.
What I would like to do is create a project with the most important 50 tasks, so that, if any of the information about these 50…
Chris Waller
- 11
- 1
0
votes
1 answer
PWA 2016 enterprise custom field - Project Health Formula Error
IIf([% Complete] = 100, "Completed", Switch(([Finish] - Date()) < 75%, "complete within 45 days of finish", ([Finish] - Date()) > 90%, "complete within 20 days of finish", ([Finish] - Date()) >= 0, "On Schedule", ([Finish] - Date()) >= 0, "Future…
Bue
- 1
0
votes
2 answers
MS Project : How to debug when "level all" freezes
I have a project with sub-projects which have sub-projects. I'm sharing the resources from one other project file.
I'm trying to level all the resources but MS Project freezes and it never ends.
How could I debug that and find a way to solve the…
emmguyot
- 21
- 2
0
votes
1 answer
Leveling Algorithm appears to be taking Total Slack into account when it should not. Why?
I have set Leveling Order to be Priority, Standard. Therefore I expected the hierarchy of leveling tests to be as follows
Is the Priority of any of the contending tasks 1000?
Are any of the contending tasks Manually scheduled?
Have any of the…
Eric
- 111
- 6
0
votes
1 answer
Gantt Chart Style Change for 2016
I have just changed over to MS Project 2016 Pro from 2010 and have noticed that the Gantt Style is different. The better aesthetic look of the rounded bars and shading in 2010 has gone in 2016.
Does anyone know how I can get them in…