IIf([% Complete] = 100, "Completed", Switch(([Finish] - Date()) < 75%, "complete within 45 days of finish", ([Finish] - Date()) > 90%, "complete within 20 days of finish", ([Finish] - Date()) >= 0, "On Schedule", ([Finish] - Date()) >= 0, "Future Project"))
Yellow: less than 75% complete within 45 days of finish Red: less than 90% complete within 20 days of finish Blue: 100% complete Green: achieving % complete targets Black: Future Projects