I have 2 tasks like Task A and B. Task A has 2 Subtask named A1 and A2 and the same for Task B(B1 and B2). Task B1 needs Task A1 to be done befor starting and Task B2 needs Task B1 to be done before starting. Actually I have dozens of these type of tasks and I can't link them all one by one. If I just link the Summary tasks together then Microsoft project will calculate the subtasks dependencies for me too ?
Here is an example. In animation studios first we Draw something as reference then we will start modeling of it so I have 2 summary tasks named : Designing and Modeling.
If I have 100 object to Design then how can I create my Project plan !?