I have task B which cant start until task A is finished (FS) but must end with task C end date (FF)(i.e. duration of B might be floating depending on the end of task A and end of task C) .. is this achievable on msproject?
Asked
Active
Viewed 58 times
1 Answers
1
It sounds like you may need a "Hammock" task, which is something that I asked about some time ago on this site. The original question (and associated answers) are here: In MS Project, can I create a task whose duration depends on two milestones? .
Iain9688
- 6,858
- 4
- 23
- 50