6

In my company, if there is any delay in the schedule I need to report the delay-reason and countermeasure. Sometimes this delay happens because of scope change.

My question is: Should I report it as "delay" in that case what would be the countermeasure? or I should just report updating the schedule without reporting delay?

Danny Schoemann
  • 4,542
  • 3
  • 25
  • 45
Sharif
  • 163
  • 4
  • Do you maybe mean consequence, if not, what do you mean by countermeasure? – Danny Schoemann Dec 02 '18 at 06:19
  • Can you give an example for a countermeasure? For example for a delay caused by a supplier not delivering on time (or reporting a delay on heir end). – Bart van Ingen Schenau Dec 02 '18 at 09:25
  • Doesn't countermeasure mean mitigation / remediation? I think he's talking about schedule recovery. – David Espina Dec 02 '18 at 13:31
  • the delay in schedule could happen due to different reasons, for example : in-accurate estimation, due to communication issue, not enough buffer time, external dependency or blocker not resolved in due time etc. so in counter measure we normally report what action we have taken so that we can avoid the situations next time . – Sharif Dec 03 '18 at 07:33

1 Answers1

6

If you had a scope change, a legitimate one that was approved via your change process, then you should also have a corresponding and proportional schedule and cost change. This means that the delay is not a delay but rather a new schedule target. Your first schedule baseline goes away as if it never existed. Same as your scope baseline and cost baseline.

If you didn't change your schedule or cost with this scope change, then your change process is broken.